Praxair Air Stripper Facility - MI

Project Cost: $120 million

Services Provided:

Schedule delay analysis.

Representative Heavy Industrial Projects

NY Post Production Facility - NY

Project Cost: $75 million

Services Provided:

Change order review; litigation support.

Kaiser Alumina Refinery - LA

Project Cost: $300 million

Services Provided:

Schedule delay analysis

Limestone Crushing Facility - MO

Project Cost: $10 million

Services Provided:

Change order analysis

Methane Gas Storage Sphere Rehabilitation - NY

Project Cost: $12 million

Services Provided:

Construction management

District #6 Sanitation Garage - NY

Project Cost: $25 million

Services Provided:

CPM Scheduling with monthly updating; delay analysis.